Penfield Library Phase 1

*https://www.facebook.com/penfieldlib/https:/
/www.pinterest.com/pin/27092035228968372/
https://www.oswego.edu/library/issue/issue-26

Construction Scheduling NYC

Delay Analysis and CPM Construction Scheduling NYC “Penfield Library Phase 1”

 

Pearls provided Construction Scheduling NYC. CPM Consultants developed the comprehensive detailed construction CPM baseline Schedule on Primavera in NY.
CPM scheduling is a project modeling technique for scheduling a set of project activities. It requires gathering sufficient data about the activities, as specified in the contract pertaining to the project. Followed by identifying their logical sequence and dependencies on one another, the type of connections between them, and their expected durations and lead time.

Project’s Location: New York

“Critical Path Method” Construction Scheduling NYC and Resource Loading included:

“Developing Work Breakdown Structures (WBS)”. First, WBS is used to list all utility, engineering, and construction activities that are broken down by phases, areas, and types of work.
It included also running several what-if scenarios. In order to optimize the sequence of operations and developing the logic, sequence, and diagrams to avoid high float values. Then, Our Consultants in New York tested and analyzed the longest path of the project, assigned direct Crew to all construction activities, and identify man-hours throughout the job. Furthermore, They provided the status of potential resources available and their feasibility to the project in New York and developed and analyzed the resource profile histogram to level resources.

Construction Delay Analysis and Time Extension Claims in New York:

The team of Construction Scheduling NYC has also worked on successful Delay analysis and time extension claims.
1- Risk and delays assessment
2- Identify major areas of slippage
3- Delay impact analysis and recovery actions
4- Develop narrative report; shall include activities started in the month (with actual start dates), activities completed during the month (with actual start and completion dates), activities in progress (with estimated remaining durations), and activities scheduled to start in the following month (with estimated start dates).
A list of approved logic changes, a list of proposed logic changes, new activities, and deleted activities.
The Construction Scheduling NYC Team provided recommendations for adjusting the Construction Progress Schedule to meet contractual milestone completion dates (includes why the schedule needs to be adjusted, e.g., change orders in the construction schedule, weather delays, contractor resources, etc.)

Looking for a reliable construction consultant for your project?