Bronx Community College Gould Memorial Library

*https://commons.wikimedia.org/wiki/File:Interior_of_Gould_Memorial_Library,_Bronx_Community_College.jpg
https://archpaper.com/2016/10/building-day-gould-memorial-library/

CPM Scheduling Consultants NYC

CPM Consultants and Construction Schedulers NY “Bronx Community College Gould Memorial Library Roof Restoration”


Project’s Location:
New York City

Value: $10M

Our Team in New York provided a CPM schedule. They developed a comprehensive detailed time CPM schedule on Primavera P6 scheduling software. They developed monthly construction schedule progress updates and construction Schedule cost analysis.

Construction CPM “Critical Path Method” Scheduling included:

“Developing Work Breakdown Structures (WBS)”. First, WBS is used to list all utility, engineering, and construction activities are broken down by phases, areas, and type of work.
It included also running several what-if scenarios. In order to optimize the sequence of operations and developing the logic, sequence, and diagrams to avoid high float values. Then, Our CPM Scheduling Consultants NYC tested and analyzed the longest path of the project, assigned direct Crew to all construction activities, and identify man-hours throughout the job. Furthermore, They provided the status of potential resources available and their feasibility to the project in New York and developed and analyzed the resource profile histogram to level resources.

Resource Loading in Construction Schedule included:

First, Assigning direct Crew to all construction activities and identify man-hours throughout the job.
Then, Providing the status of potential resources availability and their feasibility for the project.
Finally, Developing and analyzing the resource profile histogram to level resources.

Construction Delay Analysis and Time Extension Claims in NY:

The construction management team in NYC has also worked on successful Delay analysis and time extension claims.
1- Risk and delays assessment
2- Identify major areas of slippage
3- Delay impact analysis and recovery actions
4- Develop narrative report; shall include activities started in the month (with actual start dates), activities completed during the month (with actual start and completion dates), activities in progress (with estimated remaining durations), and activities scheduled to start in the following month (with estimated start dates).
A list of approved logic changes, a list of proposed logic changes, new activities, and deleted activities.
Recommendations for adjusting the Construction Progress Schedule to meet contractual milestone completion dates (includes why the schedule needs to be adjusted, e.g., change orders in the construction schedule, weather delays, contractor resources, etc.)

Looking for a reliable construction consultant for your project?