“Developing Work Breakdown Structures (WBS)”. WBS is used to list all utility, engineering, and construction activities are broken down by phases, areas, and type of work.
It included running several what-if scenarios to optimize the sequence of operations and developing the logic, sequence, and diagrams to avoid high float values. Our Consultants in Los Angeles, California tested and analyzed the longest path of the project, assigned direct Crew to all construction activities, and identify man-hours throughout the job. They also provided the status of potential resources available and their feasibility to the project in Los Angeles, California, and developed and analyzed the resource profile histogram to level resources.
They worked on with schedule cost loading, manpower and resources loading, cash flow projection, monitoring cost performance, and also monthly construction-schedule updates.
Resource Loading in Construction Schedule in Los Angeles, California included:
1- Assigning direct Crew to all construction activities as well as identifying man-hours throughout the job.
2- Providing the status of potential resources available and also their feasibility to the project.
3- Developing and analyzing the resource profile histogram to level resources.
Work Scope:
Removing and placing concrete canal panels as well as fiber reinforced concrete reservoir liner.
Repairing siphon head-walls, replacing chain link fence, constructing two concrete pads, constructing one access ramp, and also other appurtenant work